Project overview
Eneraque was contracted to design, supply, install, commission and provide on-going support for a 715kVA Standby Generator including a 4-hour fire rated 3,500 litre bulk tank and relocation of existing 400kVA generator for St Andrew’s Ipswich Hospital.Project Highlights
- 715kVA standby generator
- 715kVA bunded tank
- Temporary generator delivered & installed
- Fuel transfer pump & controls installed, pipework run to roof
- Existing 410kVA generator decommissioned
- New fire-rated bulk fuel tank
- New cabling pre-installed for generators
- Site preparation including lifting plans, road closures and Energex powerline disconnections
- New cabling pre-installed for Generators
- Installation of new and existing generators onto roof
- Testing and commissioning of both generators and fuel system