Queensland Mining Pit Dewatering Project

Project overview

To design, manufacture and commission 2 x high pressure pumps to dewater the major operating pits of the mine-site.

Our involvement

• Design – The skid-mounted pump and pipework • Manufacture – Within 8 weeks • Commission – On-site for 5 days, providing training, setup and start-up commissioning

Outcome and benefits

• High performance pump dewatered pit so that mining operations could continue • Fuel efficient at optimum performance • Reliable product, fully supported in the field

Ready to reach your energy goals?

Backed by more than 40 years' experience, our specialist energy team are here to power your project forward.